- From the menu on the left, choose Planning -> Projects.
- Select the project you want, then click the Cards tab at the top of the screen.
- Click on the desired card name.
- Click the Planned consumption section.
- Click the + Add icon.
- Enter the requested information.
The planned consumption behavior can be either Standard or Phantom.
Standard: Planned consumptions have no special interaction in this mode.
Phantom: When copying a model, allows to copy the planned consumptions with their hierarchy. This option can only be selected if the target item is produced. - Click Add when you are done.