Selling price & cost price

Total = Talents + Equipment + Material + Subcontracting

Sell price

Talents Sell Price Talents Hourly Rate x Talent Step Planned Hours
Equipment Sell Price Equipment Hourly Rate x Equipment Step Planned Hours
Material (Unit Cost + Markup) x Planned Mesure
Subcontracting Planned Subcontracts Cost+ Markup

Cost price

Talents Cost Talents Hourly Rate + Fringe x Talent Actual Hours
Equipement Cost Equipement Hourly Rate x Equipment Actual Hours
Material Actual Unit Cost x Actual Mesure
Subcontracting Actual Subcontracts Cost

Where to find the data for these calculations

(in alphabetical order)

Actual Mesure Operations -> Choose a card -> Consumption ->Measure column of the Consumed Material section

Actual Subcontracts Cost Planning -> Projects -> Choose a project -> Cards -> Choose a Cards -> Subcontracts

Actual Unit Cost Planing -> Projects -> Choose a project -> Project Material -> Choose an inventory -> Informations

Cost Equipement Hourly Rate Equipments -> Equipments -> Choose an equipment

Cost Talents Hourly Rate Talents -> Talents -> Choose a talent

Equipment Actual Hours Operations -> Choose a card -> Steps -> Actual Equipment Column

Equipment Step Planned Hours Operations -> Choose a card -> Steps -> Equipment Column

Fringe Talents -> Talents -> Choose a talent

Markup Planning -> Projects -> Choose a project

Planned Mesure Operations -> Choose a card -> Consumption -> Measure column of the Planned Consumption section

Planned Subcontracts Cost Planning -> Projects -> Choose a project -> Cards -> Choose a Cards -> Subcontracts

Sell Price Equipment Hourly Rate Settings -> Settings -> Value Streams

Sell Price Talents Hourly Rate Settings -> Settings -> Value Streams

Talent Actual Hours Operations -> Choose a card -> Steps -> Actual Talent Column

Talent Step Planned Hours Operations -> Choose a card -> Steps -> Talent Column

Unit Cost Items -> Choose an item -> Accounting

For items purchased with a preferred supplier:

Otherwise: