Set up manual reorder point by item #
With ALIX, it is possible to configure manual reorder points per item. These settings allow for better inventory and projects planning. It is possible to configure a global scope or a per-site scope.
By default, items are configured to make to order/ buy to order: the values are all at 0.
- From the menu on the left, choose Items.
- Click on the desired item. The information of the item appears on the screen.
- In the menu on the left side of the item, click the Planning section.
- Click the + button.
- Select the scope: global or choose a site, then click Confirm.
- Enter the informations:
Field Description Safety stock The minimum acceptable stock level for an item. Reorder point Below this stock level, a new order must be placed with production or with a supplier. Maximum stock level The maximum acceptable stock level for an item. - Once done, exit by clicking on the X in the top right. The information is backed up automatically.
Recommend project demand instead of net flow in planning #
In project planning, it is possible to choose which criterion will be used to calculate the recommendation:
Toggle button off | Recommendation is based on each item reorder points (default configuration) |
Toggle button on | Recommendation is based on the project demand |
- In Settings, go to Settings, Configurations, then Project.
- Choose Recommend project demand instead of net flow in planning.